In 1992 — three years after starting their business — Technical Drilling Services became one of the first engineering companies in New England to purchase a Geoprobe®

“We made a huge leap of faith to buy the Geoprobe® — not yet proven in the glacial till of New England. Contemporaries were laughing at me,” Mark Zork, president, said. “Thirty years later if you don’t have a Geoprobe® in your arsenal you’ll be missing out.”

Now with seven Geoprobe® rigs ranging from 420M to 7822DT with coring capabilities, they use smaller rigs for niche stuff inside buildings and larger rigs on big direct push projects. For two years they used a 7822DT and a 6712DT exclusively on a PFAS water testing investigation at the former Fort Devens Army Base in Massachusetts, which is now used as a commercial/industrial center.

“The site has a highly permeable soil with a deep water table. Past use of the property contaminated hundreds of acres with PFAS. They filled lagoons with diesel fuel, lighting them to practice putting out jet fuel fires with retardants containing PFAS,” Zork said. “The highly permeable soil conditions caused the contamination impact. There’s concern whether the two or three municipal well supplies adjacent to this facility have been impacted.”

Using the two rigs for two years, they conducted groundwater profiles with water sampling every 10 feet, initially using SP16 and eventually switching to SP22.

“We kept finding PFAS so they kept adding change orders to expand the area sampled until we had peppered the base with groundwater profiling,” Zork said.

During the PFAS water testing project they conducted numerous holes to more than 100 feet, including a 181-foot vertical profile using SP22. 

“We had similar production rates between the 7822DT and 6712DT,” Zork said. 

According to Zork, the Environmental Protection Agency, local Massachusetts Department of Environmental Protection, along with the Army Corps of Engineers collaborated on the scope of work. After the agencies had tried sonic — which achieved depths quickly but struggled sampling to the point they didn’t trust the results — they revised the work plan to direct push using SP16. However, Zork experienced challenges with the 1.5-inch rods in the soft soil.

“We would bend a string of rods 100-foot long, looking like a corkscrew when we pulled them out. The rods would be straight for 50 feet and then bend without an indication in hammer production we’d hit an obstacle,” Zork said. “Because of the soil between 70-150 feet, we wouldn’t know what direction they were going. It got to where I would call Geoprobe® because we’d lost 150 feet of rod and began keeping 300 feet of rod in stock at all times.”

After six months of SP16, the agencies switched the scope of work to SP22 using a heavier rod, which eliminated the rod bending. SP16 and SP22 were specified because of their ability to isolate the sample in a closed system.

“We could go through 100 feet of water with confidence of the discrete nature of the sample, important because the detectable carcinogenic rate is so low you have to be certain there’s no cross contamination,” Zork said. “SP22 handled filtering out fine sediments better than SP16.”

They were required to complete a sampling protocol without injecting another water source into the sample.

“Normally we would wash out heaving sands to keep them from coming up in the drill rod, but we had to have a means of taking samples without introducing water into the sample,” Zork said. “There was zero tolerance for introducing water into the casing.”

That zero tolerance applied to rain water as well. 

“If there was heavy rainfall with droplets running off our heads or equipment, they would shut down the site. Not because of the rain but because something we had on or with us would have a chance of cross contamination by dripping into the samples,” Zork said. “We had to document that the sampling equipment didn’t contain PFAS. Because detection levels are so much lower, they had to eliminate any chance we were introducing something that wasn’t in the ground.”

The direct push method and use of SP16 and SP22 were the only way to complete the PFAS water testing project in Zork’s mind.

“The job couldn’t have been done with a conventional machine or other method of drilling. SP16 and SP22 are proven sampling methods,” Zork said. “In most situations the EPA and Army Corps are already educated to how useful these tools are. Geoprobe® has done the right demonstrations for the right people.”

The 7822DT and 6712DT also proved to be the right tools, minimizing downtime on the two-year project to just 10 days – only two due to breakdowns.

“I finally told the client the rigs had been running virtually non-stop for four months and we needed to do regular maintenance on hydraulics and engine oil,” Zork said. “Downtime is the biggest killer in the industry. Geoprobe® has done their homework and the tech support is so far superior. Geoprobe® products may not be cheapest, but being able to depend on them to run is more important.”

Upon completion, Phase I of this PFAS water testing project had ballooned into a $1 million direct push job. The agencies recently contacted Zork to conduct another round of groundwater sampling — 15 profiles to bedrock estimated at 150 to 200 feet, all direct push. The proposed second contract is $200,000.

“We’ve been in business 33 years,” Zork said. “Thirty-three years ago I didn’t even realize if I’d still be in business or if I’d be dead or sipping pina coladas on a beach somewhere.”

Contact Us

1835 Wall Street
Salina, Kansas 67401
Phone: (785) 825-1842

SP22-ISP Groundwater Sampler

6712DT direct push drill rig

6712DT Drill Rig

Engineered to separate into sections for helicopter transport, the 6712DT leverages its Tier 4 engine for additional power and control to make environmental work easier.

Related Articles


When your rig is out of commission, it’s important to get the support and replacement parts you need as quickly as possible. But when your rig specialist is in another country, it’s not just speed that matters – it’s also product knowledge.

ID: 14086 | Date:

Geoprobe® machines feature safe, intuitive, and user-friendly controls for a fast learning curve for operators as well as drop racks and storage options for convenient tooling access.

ID: 14036 | Date:

Regular maintenance and assistance from international service team keeps rigs running smoothly for our international customers.

ID: 14029 | Date:

OIP-UVR provides added confidence when detecting lighter-end jet fuels.

ID: 14028 | Date:

The small footprint of the 6011DT slides into tight indoor spaces for site investigations.

ID: 14026 | Date: